Glasgow Closing of Private Sewer ordinance (§ 700.310)
Chapter 700: Water and Sewer · Article IV. Sewer Regulations
In short: Once a public sewer becomes available, property owners must connect the building sewer to it within 60 days, then clean the sludge out of the private sewage disposal system and fill it with clean bank-run gravel or dirt.
Our plain-English summary, not the official text or legal advice. The ordinance below is what counts.
When a public sewer becomes available, the building sewer shall be connected to said sewer within sixty (60) days and the private sewage disposal system shall be cleaned of sludge and filled with clean bank-run gravel or dirt.
Official source: City of Glasgow official Code of Ordinances (online), § 700.310
Last checked November 1, 2026. The city's official copy controls; this page is a reading copy, not legal advice.