Fayette Time Limitation on Certificate of Appropriateness ordinance (§ 415.460)

Chapter 415: Historic Districts and Landmarks · Article V. Certificates of Appropriateness and Certificates of Economic Hardship

A certificate of appropriateness shall become void unless construction is commenced within six (6) months of date of issuance. Certificates of appropriateness shall be issued for a period of eighteen (18) months and are renewable. If the project is not completed according to the guidelines provided in the certificate of appropriateness, the project shall be deemed in violation of this Article.

Official source: City of Fayette official Code of Ordinances (online), § 415.460

Last checked October 30, 2026. The city's official copy controls; this page is a reading copy, not legal advice.