Boonville Wastewater discharge permit appeals ordinance (§ 21-253)
Chapter 21: Waters, Sewers and Solid Waste Disposal · Division 5. Wastewater Discharge
The superintendent shall provide public notice of the issuance of a wastewater discharge permit. Any person, including the user, may petition the superintendent to reconsider the terms of a wastewater discharge permit within 90 days of notice of its issuance.
(1) Failure to submit a timely petition for review shall be deemed to be a waiver of the administrative appeal.
(2) In its petition, the appealing party must indicate the wastewater discharge permit provisions objected to, the reasons for this objection, and the alternative condition, if any, it seeks to place in the wastewater discharge permit.
(3) The wastewater discharge permit shall not be stayed pending the appeal.
(4) If the superintendent fails to act within 90 days, a request for reconsideration shall be deemed to be denied. Decisions not to reconsider a wastewater discharge permit, not to issue a wastewater discharge permit, or not to modify a wastewater discharge permit shall be considered final administrative actions for purposes of judicial review.
(5) Aggrieved parties seeking judicial review of the final administrative wastewater discharge permit decision must do so by filing a complaint with Circuit Court of Cooper County, Missouri within the State Statute of Limitations as prescribed by Missouri law.
Official source: City of Boonville official Code of Ordinances (online): look up Sec. 21-253
Text from Supplement 8 (December 2025), through Ordinance 4678 of December 16, 2024.
Last checked October 30, 2026. The city's official copy controls; this page is a reading copy, not legal advice.